GASHCO Bund Wall Project

GASHCO (Gatwick Airport Storage & Hydrant Company) have recently awarded the £900k contract for the GASHCO Bund Wall Project – Modifications, the works over a 19 week period will consist of Extension to existing bund wall of approx 150m of new reinforced concrete wall and 3670m² new floor slab with integral drainage, to increase emergency fuel storage capacity. Works include new 400mm fire water drain which extends airside to tie into existing system.